A.45 Missoula County, MT

Milltown Reservoir Sediments Operable Unit, Missoula County, MT (CERCLIS ID #MTD980717565)

A.45.1 Contacts

Diana Hammer, USEPA (Region 8, Lead Agency), 406-457-5040, [email protected]

Keith Large, MT DEQ (Supporting Agency), 406-841-5039, [email protected]

A.45.2 Summary

Environment:

Freshwater reservoir

Scale:

Full

Contaminants of Concern:

Groundwater: arsenic, cadmium, copper, lead, zinc, and mercury

Surface water: arsenic, cadmium, copper, lead, and zinc

Source Control Achieved Prior to Remedy Selection?

No

Final Remedy:

Sediment removal (approximately 2.2 million yd3) and MNR (approximately 540 acres)

Expected Recovery Time:

4-10 years beginning in 2011

MNR viewed as a success?

Yet to be determined

A.45.3 Site Description

Primary source(s): For nearly one-hundred years, mine wastes were discharged into the headwaters of the Clark Fork River and after 1908, came to rest behind the Milltown Dam. In the same year, the largest flood on record in the area washed the mining waste into the Milltown Reservoir, creating approximately 6.6 million yd3 of contaminated reservoir sediments.

Location:The Milltown Reservoir Sediments Operable Unit (MRSOU) is one of three operable units, which also includes the Clark Fork River and Milltown Water Supply, near Milltown, Montana. The MRSOU covers approximately 540 acres (as defined by the area inundated by the maximum pool elevation of 3,263.5 ft).

Beginning in the 1860s, mine wastes were discharged to the headwaters of the Clark Fork River. In 1908, the Milltown Dam was constructed. In the same year, mine waste that had accumulated behind the dam was flushed into the Milltown Reservoir by a large flood. From here, the mine waste contaminated the local drinking water source.

In September 1983, the Milltown Reservoir was added to the National Priorities List (NPL). A year later, the city of Milltown installed a new water system. Remediation studies and investigations dominated activity at the site into the 2000s. The EPA issued a ROD in December 2004. It stressed a 3-R approach: remediationThe act or process of abating, cleaning up, containing, or removing a substance (usually hazardous or infectious) from an environment., restoration, and redevelopment. In August 2005, a Consent Decree identifying Atlantic Richfield Company and NorthWestern Corporation as the site’s responsible parties, was signed.

In the fall of 2006, remediation of the Superfund site began. Concurrent restoration of the site began in 2008. In 2009, sediment removal from the Milltown Reservoir was completed. By February 2010, the Milltown dam had been removed. Remediation action construction activities are ongoing and are expected to be completed in the near future (approximately a year).

CSM summary: The primary source of COCs in the Milltown Reservoir is contaminated sediment. Secondary sources of COCs are exposed aquatic flora and fauna, surface water, and suspended sediment transported from the Clark Fork River.

A.45.4 Remedial Objectives

The MRSOU poses risks to human health via ingestion of contaminated potable groundwater and ingestion of aquatic life. Risks exist for flora and fauna directly and indirectly exposed to COCs.

RAOs/Project objectives: Remediation of the MRSOU is twofold: (1) reduction or elimination of the groundwater arsenic plume and (2) risk reduction to aquatic life. RAO’s exist for groundwater and surface water at the site.

The groundwater RAOs, as reported in the site’s ROD, are as follows:

Temporary and long-term surface water RAOs were developed for the MRSOU. The temporary RAOs waive ambient surface water standards for cadmium, copper, zinc, lead, arsenic, iron, and total suspended solids during the construction phase. The long-term surface water RAOs, as reported in the site’s ROD, are as follows:

Additionally, performance standards exist for 1) the protection of waste left in place and local repositories, 2) the new channel, and 3) re-vegetation of river banks and the flood plain. Notably, the site will be redeveloped as a state park.

A.45.5 Remedial Approach

Final selected remedy: Remedy alternative 7A2, modified: partial dam removal with partial sediment removal of the Lower Reservoir plus Groundwater ICs and natural attenuation within the aquifer plume.

Remedy Selected alternative 7A2, modified consists of many phases. The major remedial elements, as reported in the ROD, are as follows:

Advantages of the selected remedy:

Remedy alternative 7A2, modified was selected for the following reasons:

Disadvantages of the selected remedy:

The following limitations or disadvantages exist for remedy alternative 7A2, modified:

Expected recovery time: The selected remedy will allow recovery of the Milltown/Bonner aquifer within 4-10 years.

A.45.6 Monitoring

Monitoring elements: In addition to monitoring that occurred during the remedial action, O&M activities will take place for at least five years after construction has been completed in order to ensure that performance standards are being met.

The Statement of Work for Milltown Reservoir requires that a long-term monitoring plan be developed at least 60 days prior to the completion of remediation action construction activities. Such a plan has not yet been written.

RAOs/project objectives achieved: The success of MNR at the MRSOU is yet to be determined.

A.45.7 Costs

Projected monitoring costs: N/A

Net present value for project costs: $106,000,000 (discounted by 3% per year for the estimated life of the project)

A.45.8 References

USEPA. Integrating the “3 Rs”: Remediation, Restoration and Redevelopment, the Milltown Reservoir Sediment Site and Missoula County, Montana. April 2011. Available at www.epa.gov/region8/superfund/mt/milltown/2011ReadyForReuseFactSheet.pdf.

USEPA. Record of Decision: Milltown Reservoir Sediments Operable Unit of the Milltown Reservoir/Clark Fork River Superfund Site. December 2004. Available at www.epa.gov/region8/superfund/mt/milltown/mrsrod.html.

USEPA. Superfund Program Record of Decision Factsheet: Milltown Reservoir Sediments Operable Unit of the Milltown Reservoir/Clark Fork River Superfund Site. No date. Available at www.epa.gov/region8/superfund/mt/milltown/pdf/mrsRODfs.pdf..

Envirocon. Repository Operation and Monitoring Plan, Milltown Reservoir Sediments Operable Unit, Final. February 3, 2010.

Publication Date: August 2014

Permission is granted to refer to or quote from this publication with the customary acknowledgment of the source (see suggested citation and disclaimer).

 

This web site is owned by ITRC.

1250 H Street, NW • Suite 850 • Washington, DC 20005

(202) 266-4933 • Email: [email protected]

Terms of Service, Privacy Policy, and Usage Policy

 

ITRC is sponsored by the Environmental Council of the States.